APR1400
Power Plant | Location | Capacity(MW) | Engineering | Construction Period (First Concrete Placement – Commercial Operation) |
Note |
---|---|---|---|---|---|
Shin-Kori Unit 3 |
Uljin-gun, Gyeongsangbuk-do |
1,400 |
KEPCO E&C |
2008.10 ~ 2016.12 |
In Operation |
Shin-Kori Unit 4 |
Uljin-gun, Gyeongsangbuk-do |
1,400 |
KEPCO E&C |
2009.10 ~ 2019.09 |
Under Construction |
Shin-Kori Unit 5 |
Ulju-gun, Ulsan-si |
1,400 |
KEPCO E&C |
2017.04 –2023.03 |
Under Construction |
Shin-Kori Unit 6 |
Ulju-gun, Ulsan-si |
1,400 |
KEPCO E&C |
2018.10 –2024.06 |
Under Construction |
Shin-Hanul Unit 1 |
Shin-Hanul Unit 1 |
1,400 |
KEPCO E&C |
2012.08 ~ 2019.11 |
Under Construction |
Shin-Hanul Unit 2 |
Uljin-gun, Gyeongsangbuk-do |
1,400 |
KEPCO E&C |
2013.08 ~ 2020.09 |
Under Construction |
BNPP Unit 1 |
Al Barakha, the UAE |
1,400 |
KEPCO E&C |
2012.07 ~ 2018.12 |
Under Construction |
BNPP Unit 2 |
Al Barakha, the UAE |
1,400 |
KEPCO E&C |
2013.04 ~ 2019.08 |
Under Construction |
BNPP Unit 3 |
Al Barakha, the UAE |
1,400 |
KEPCO E&C |
2014.09 ~ 2020.04 |
Under Construction |
BNPP Unit 4 |
Al Barakha, the UAE |
1,400 |
KEPCO E&C |
2015.07 ~ 2020.12 |
Under Construction |
-
- Power Plant
- Shin-Kori Unit 3
- Location
- Uljin-gun, Gyeongsangbuk-do
- Capacity(MW)
- 1,400
- Engineering
- KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 2008.10 ~ 2016.12
- Note
- Under Construction
-
- Power Plant
- Shin-Kori Unit 4
- Location
- Uljin-gun, Gyeongsangbuk-do
- Capacity(MW)
- 1,400
- Engineering
- KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 2009.10 ~ 2019.09
- Note
- Under Construction
-
- Power Plant
- Shin-Kori Unit 5
- Location
- Ulju-gun, Ulsan-si
- Capacity(MW)
- 1,400
- Engineering
- KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 2017.04 –2023.03
- Note
- Under Construction
-
- Power Plant
- Shin-Kori Unit 6
- Location
- Ulju-gun, Ulsan-si
- Capacity(MW)
- 1,400
- Engineering
- KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 2018.10 –2024.06
- Note
- Under Construction
-
- Power Plant
- Shin-Hanul Unit 1
- Location
- Shin-Hanul Unit 1
- Capacity(MW)
- 1,400
- Engineering
- KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 2012.08 ~ 2019.11
- Note
- Under Construction
-
- Power Plant
- Shin-Hanul Unit 2
- Location
- Uljin-gun, Gyeongsangbuk-do
- Capacity(MW)
- 1,400
- Engineering
- KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 2013.08 ~ 2020.09
- Note
- Under Construction
-
- Power Plant
- BNPP Unit 1
- Location
- Al Barakah, the UAE
- Capacity(MW)
- 1,400
- Engineering
- KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 2012.07 ~ 2018.12
- Note
- Under Construction
-
- Power Plant
- BNPP Unit 2
- Location
- Al Barakah, the UAE
- Capacity(MW)
- 1,400
- Engineering
- KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 2013.04 ~ 2019.08
- Note
- Under Construction
-
- Power Plant
- BNPP Unit 3
- Location
- Al Barakah, the UAE
- Capacity(MW)
- 1,400
- Engineering
- KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 2014.09 ~ 2020.04
- Note
- Under Construction
-
- Power Plant
- BNPP Unit 4
- Location
- Al Barakah, the UAE
- Capacity(MW)
- 1,400
- Engineering
- KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 2015.07 ~ 2020.12
- Note
- Under Construction
OPR1000
Power Plant | Location | Capacity (MW) | Engineering | Construction Period (First Concrete Placement – Commercial Operation) |
Note |
---|---|---|---|---|---|
Hanbit Unit 3 |
Yeonggwan-gun, Jeollanam-do |
1,000 |
KEPCO E&C/WEC |
1989.12 ~ 1995.03 |
In Operation |
Hanbit Unit 4 |
Yeonggwan-gun, Jeollanam-do |
1,000 |
KEPCO E&C/WEC |
1990.06 ~ 1996.01 |
In Operation |
Hanul Unit 3 |
Uljin-gun, Gyeongsangbuk-do |
1,000 |
KEPCO E&C |
1993.07 ~ 1998.08 |
In Operation |
Hanul Unit 4 |
Uljin-gun, Gyeongsangbuk-do |
1,000 |
KEPCO E&C |
1993.11 ~ 1999.12 |
In Operation |
Hanbit Unit 5 |
Yeonggwan-gun, Jeollanam-do |
1,000 |
KEPCO E&C |
1997.06 ~ 2002.05 |
In Operation |
Hanbit Unit 6 |
Yeonggwan-gun, Jeollanam-do |
1,000 |
KEPCO E&C |
1997.11 ~ 2002.12 |
In Operation |
Hanul Unit 5 |
Uljin-gun, Gyeongsangbuk-do |
1,000 |
KEPCO E&C |
1999.10 ~ 2004.07 |
In Operation |
Hanul Unit 6 |
Uljin-gun, Gyeongsangbuk-do |
1,000 |
KEPCO E&C |
2000.10 ~ 2005.04 |
In Operation |
Shin-Kori Unit 1 |
Gijang-gun, Busan |
1,000 |
KEPCO E&C |
2006.06 ~ 2011.02 |
In Operation |
Shin-Kori Unit 2 |
Gijang-gun, Busan |
1,000 |
KEPCO E&C |
2007.06 ~ 2011.12 |
In Operation |
Shin-Wolsong Unit 1 |
Gyeongju-si, Gyeongsangbuk-do |
1,000 |
KEPCO E&C |
2007.12 ~ 2012.03 |
In Operation |
Shin-Wolsong Unit 2 |
Gyeongju-si, Gyeongsangbuk-do |
1,000 |
KEPCO E&C |
2008.12 ~ 2013.08 |
In Operation |
-
- Power Plant
- Hanbit Unit 3
- Location
- Yeonggwan-gun, Jeollanam-do
- Capacity(MW)
- 1,000
- Engineering
- KEPCO E&C/WEC
- Construction Period(First Concrete Placement –
Commercial Operation) - 1989.12 ~ 1995.03
- Note
- In Operation
-
- Power Plant
- Hanbit Unit 4
- Location
- Yeonggwan-gun, Jeollanam-do
- Capacity(MW)
- 1,000
- Engineering
- KEPCO E&C/WEC
- Construction Period(First Concrete Placement –
Commercial Operation) - 1990.06 ~ 1996.01
- Note
- In Operation
-
- Power Plant
- Hanul Unit 3
- Location
- Uljin-gun, Gyeongsangbuk-do
- Capacity(MW)
- 1,000
- Engineering
- KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 1993.07 ~ 1998.08
- Note
- In Operation
-
- Power Plant
- Hanul Unit 4
- Location
- Uljin-gun, Gyeongsangbuk-do
- Capacity(MW)
- 1,000
- Engineering
- KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 1993.11 ~ 1999.12
- Note
- In Operation
-
- Power Plant
- Hanbit Unit 5
- Location
- Yeonggwan-gun, Jeollanam-do
- Capacity(MW)
- 1,000
- Engineering
- KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 1997.06 ~ 2002.05
- Note
- In Operation
-
- Power Plant
- Hanbit Unit 6
- Location
- Yeonggwan-gun, Jeollanam-do
- Capacity(MW)
- 1,000
- Engineering
- KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 1997.11 ~ 2002.12
- Note
- In Operation
-
- Power Plant
- Hanul Unit 5
- Location
- Uljin-gun, Gyeongsangbuk-do
- Capacity(MW)
- 1,000
- Engineering
- KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 1999.10 ~ 2004.07
- Note
- In Operation
-
- Power Plant
- Hanul Unit 6
- Location
- Uljin-gun, Gyeongsangbuk-do
- Capacity(MW)
- 1,000
- Engineering
- KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 2000.10 ~ 2005.04
- Note
- In Operation
-
- Power Plant
- Shin-Kori Unit 1
- Location
- Gijang-gun, Busan
- Capacity(MW)
- 1,000
- Engineering
- KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 2006.06 ~ 2011.02
- Note
- In Operation
-
- Power Plant
- Shin-Kori Unit 2
- Location
- Gijang-gun, Busan
- Capacity(MW)
- 1,000
- Engineering
- KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 2007.06 ~ 2011.12
- Note
- In Operation
-
- Power Plant
- Shin-Wolsong Unit 1
- Location
- Gyeongju-si, Gyeongsangbuk-do
- Capacity(MW)
- 1,000
- Engineering
- KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 2007.12 ~ 2012.03
- Note
- In Operation
-
- Power Plant
- Shin-Wolsong Unit 2
- Location
- Gyeongju-si, Gyeongsangbuk-do
- Capacity(MW)
- 1,000
- Engineering
- KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 2008.12 ~ 2013.08
- Note
- In Operation
CANDU Nuclear Power Plants
Power Plant | Location | Capacity (MW) | Engineering | Construction Period (First Concrete Placement – Commercial Operation) | Note |
---|---|---|---|---|---|
Wolsong Unit 2 |
Gyeongju-si, Gyeongsangbuk-do |
713 |
AECL/KEPCO E&C |
1992.09 ~ 1997.07 |
In Operation |
Wolsong Unit 3 |
Gyeongju-si, Gyeongsangbuk-do |
715 |
KEPCO E&C/AECL |
1994.04 ~ 1998.07 |
In Operation |
Wolsong Unit 4 |
Gyeongju-si, Gyeongsangbuk-do |
715 |
KEPCO E&C/AECL |
1994.08 ~ 1999.10 |
In Operation |
-
- Power Plant
- Wolsong Unit 2
- Location
- Gyeongju-si, Gyeongsangbuk-do
- Capacity(MW)
- 713
- Engineering
- AECL/KEPCO E&C
- Construction Period(First Concrete Placement –
Commercial Operation) - 1992.09 ~ 1997.07
- Note
- In Operation
-
- Power Plant
- Wolsong Unit 3
- Location
- Gyeongju-si, Gyeongsangbuk-do
- Capacity(MW)
- 715
- Engineering
- KEPCO E&C/AECL
- Construction Period(First Concrete Placement –
Commercial Operation) - 1994.04 ~ 1998.07
- Note
- In Operation
-
- Power Plant
- Wolsong Unit 4
- Location
- Gyeongju-si, Gyeongsangbuk-do
- Capacity(MW)
- 715
- Engineering
- KEPCO E&C/AECL
- Construction Period(First Concrete Placement –
Commercial Operation) - 1994.08 ~ 1999.10
- Note
- In Operation